BISHOPS' HIGH SCHOOL
- CHESTER -
-
project outline
remove counters from Blacon High School
remodel... redesign... re-fabricate...
re-deliver to Bishops' Blue Coat High School
and re-install on the first floor
-
GET READY FOR
AWESOMENESS
A project that was allocated to the 6 week holidays
A school that was running behind schedule...
A team of professionals installing in just 6 days
Hygiene cleaned - Installed - Handed over - ON TIME
-
BLACON HIGH SCHOOL
These are the original counters at Blacon High School
Green formica fronted, tray slide and kick plates
With Moffat hot and cold counter units
-
BLACON HIGH SCHOOL
The second counter at Blacon High School
Granite topped, inset counter with dwarf wall front
and wave shape granite tray slide
-
BISHOPS' HIGH SCHOOL
These were the original counters at Bishops'
Oddly sized, uneven height servery units
with limited display area and congestion at lunch time...
-
BISHOPS' HIGH SCHOOL
This is the original second counter at Bishops
Dated equipment, functional but not efficient
Asbestos insulating panels making repairs tricky
-
BLACON SCHOOL
So we started to uninstall from Blacon...
Frontage off, Electrics Isolated and counters split
-
BLACON SCHOOL
First Counter removed succesfully
-
BLACON SCHOOL
Second counter removed
-
FABRICATION
First counter undergoing fabrication
This was the granite topped counter that has
been re-topped with 2mm stainless
and strengthened panels to take new tray slide
-
BISHOPS' SCHOOL
Upon delivery, the equipment had to come
up these stairs to the first floor canteen
Using our ingenious idea, we managed to transport
all the equipment to the first floor safely
-
BISHOPS' SCHOOL
First counter being installed in the kitchen
Stainless sheeting to the wall
Electrics hidden under the counter
And all whilst being supervised by Sarah Hewitt
-
BISHOPS SCHOOL
Black panelling installed on first counter
Custom made cutlery tray installed (customer request)
Each unit tested electrically and for functionality
-
BISHOPS SCHOOL
Second counter in position, levelled
ready for power pole to be installed
and counter front panelling.
-
BISHOPS' SCHOOL
Custom corner cabinet, twin door with
consumer unit hidden away and false back
for power pole to supply 3 phase power to board
Side glass damaged on merchandiser during transit
emergency replacement glass sourced and fitted
-
BISHOPS SCHOOL
Custom gastronorm fabrication to take 1/3
and 1/6 pans, 100mm deep with an angle of
10 degrees towards the back to make it easier
for staff to serve the subway style sandwiches
-
BISHOPS SCHOOL
Second counter being installed
On site electricians installing LED lighting
OTS still on schedule for completion
-
BISHOPS SCHOOL
Getting close now, the guys feeling the pressure
Measuring up for final trims and tweaking the
the counters where required.
-
BISHOPS SCHOOL
First counter completed, black panelling
installed, custom cutlery tray and tray slide
installed, kick boards and lift up hatch completed
Each unit final checked and sanitised
-
BISHOPS SCHOOL
Second counter completed, black panelling
installed, kick plates, till stations and power
pole installed. Trims in place and joints siliconed
Units tested and sanitised